We were first contacted in February 2015 about this project. Tanners Brook were constructing an extension to the existing building and required a Sheltered Outdoor Play Area to be attached to the new extension to provide extra space and shelter.

Aliport Commercial undertook one site visit to fully understand the project, measure up and produce the designs for the new canopy and extra’s to be installed. As extension works were being undertaken, the area where the canopy was to be installed was within the construction area and therefore consideration had to be given to the safety of the Aliport fitters and liaison with other contractors on site.

Work commenced in May 2016 and over a 2 day duration installed the canopy. The Canopy has been powder-coated Green to match the metal work within the new extension. The installation was completed successfully and matches the new extension creating a fantastic looking new addition.

May 2016

2 days

20m²

Hampshire

£0-£20k+

Other Case Studies

Contact us

Our experienced team is on hand to assist with any enquiries or questions you may have.